SKB Industries, Inc. v. Insite case brief summary
551 S.E.2d 380 (2001)
CASE FACTS
The hardscaping contractor was preparing to submit a bid to do both the hardscaping and landscaping work on a project to build a plaza. For the purpose of submitting a bid for the whole project, the hardscaping contractor received a bid from the landscaping subcontractor. The hardscaping contractor included the subcontractor's bid in its bid to do the whole project. The subcontractor then failed to substantially perform.
DISCUSSION
CONCLUSION
The judgment was affirmed in part, the judgment was reversed and the matter was remanded.
Recommended Supplements and Study Aids for Contract Law



Shop for Law School Course Materials
.
551 S.E.2d 380 (2001)
CASE SYNOPSIS
Plaintiff hardscaping contractor sued
defendant subcontractor over work on a construction project placed
for bid. A jury in the trial court, Georgia, found for the
subcontractor on this claim and awarded damages. The jury also found
for the subcontractor on its claims of tortious interference with the
subcontractor's contractual relationship with the project's general
contractor. The subcontractor appealed.CASE FACTS
The hardscaping contractor was preparing to submit a bid to do both the hardscaping and landscaping work on a project to build a plaza. For the purpose of submitting a bid for the whole project, the hardscaping contractor received a bid from the landscaping subcontractor. The hardscaping contractor included the subcontractor's bid in its bid to do the whole project. The subcontractor then failed to substantially perform.
DISCUSSION
- A claim of promissory estoppel required proof that:
- (1) the subcontractor made a promise to do the landscape work;
- (2) the subcontractor should have expected that hardscaping contractor would rely on the promise;
- (3) the hardscaping contractor did rely on the promise to its detriment; and
- (4) injustice could be avoided only by enforcement of the promise.
- The appellate court found no merit in the contention that a claim of promissory estoppel was rendered inapplicable.
- The appellate court, however, agreed with the contention that there was no evidence to support the jury's award of damages for tortious interference.
- Nevertheless, there was sufficient evidence of bad faith to create a jury issue as to the award of litigation expenses.
CONCLUSION
The judgment was affirmed in part, the judgment was reversed and the matter was remanded.
Recommended Supplements and Study Aids for Contract Law
Shop for Law School Course Materials
No comments:
Post a Comment